WO-1107 · G2 line testing voltage low, machine failing tests

WO-1107
Done

G2 line testing voltage low, machine failing tests

Priority
CRIT
Category
electrical
Assignee
Sahil
Asset
BS-054 · CHARGING M/C -G2 Line
Scheduled
—
Due
—
Created
27 Jul 2026, 08:27 am
Completed
27 Jul 2026, 09:55 am
Status
This work order is in a terminal state.
Add comment

Activity

  1. Moved to —

    assigned → completed

    In the app·27 Jul 2026

  2. Unassigned

    In the app·27 Jul 2026